SYS.5.BP3 Select test cases |
SYS.5.O.3 Test cases included in the system qualification test specification are selected according to the system qualification test strategy and the release plan |
|
|
SYS.5.BP2 Develop specification for system qualification test |
SYS.5.O.2 A specification for system qualification test of the integrated system according to the system qualification test strategy is developed that issuitable to provide evidence for compliance with the system requirements |
|
|
SYS.5.BP5 Establish bidirectional traceability |
SYS.5.O.5 Consistency and bidirectional traceability are established between system requirements and test cases included in the system qualification test specification and between test cases and test results |
|
|
SYS.5.BP4 Test integrated system |
SYS.5.O.4 The integrated system is tested using the selected test cases and the results of system qualification test are recorded |
|
|
SYS.5.BP1 Develop system qualification test strategy including regression test strategy |
SYS.5.O.1 A system qualification test strategy including regression test strategy consistent with the project plan and release plan is developed to test the integrated system |
|
|
SYS.5.BP6 Ensure consistency |
SYS.5.O.5 Consistency and bidirectional traceability are established between system requirements and test cases included in the system qualification test specification and between test cases and test results |
|
|
SYS.5.BP7 Summarize and communicate results |
SYS.5.O.6 results of the system qualification test are summarized and communicated to all affected parties |
|
|
08-50 Test specification |
SYS.5.O.2 A specification for system qualification test of the integrated system according to the system qualification test strategy is developed that issuitable to provide evidence for compliance with the system requirements |
|
|
08-50 Test specification |
SYS.5.O.3 Test cases included in the system qualification test specification are selected according to the system qualification test strategy and the release plan |
|
|
08-52 Test plan |
SYS.5.O.1 A system qualification test strategy including regression test strategy consistent with the project plan and release plan is developed to test the integrated system |
|
|
13-04 Communication Record |
SYS.5.O.6 results of the system qualification test are summarized and communicated to all affected parties |
|
|
13-19 Review Record |
SYS.5.O.5 Consistency and bidirectional traceability are established between system requirements and test cases included in the system qualification test specification and between test cases and test results |
|
|
13-22 Traceability record |
SYS.5.O.5 Consistency and bidirectional traceability are established between system requirements and test cases included in the system qualification test specification and between test cases and test results |
|
|
13-50 Test result |
SYS.5.O.4 The integrated system is tested using the selected test cases and the results of system qualification test are recorded |
|
|
13-50 Test result |
SYS.5.O.6 results of the system qualification test are summarized and communicated to all affected parties |